• ISSN: 1674-7461
  • CN: 11-5823/TU
  • Hosted by: China Society and Technology Association
  • Organizer: China Graphics Society
  • Guidance: China Academy of Building Research

Citation: Juting Tang, Hongdong Xie, Guangxing Wang, Guoping Peng. Research on Application of Construction Schedule Based on Location Management System. Journal of Information Technologyin Civil Engineering and Architecture, 2024, 16(3): 41-45. doi: 10.16670/j.cnki.cn11-5823/tu.2024.03.08

2024, 16(3): 41-45. doi: 10.16670/j.cnki.cn11-5823/tu.2024.03.08

Research on Application of Construction Schedule Based on Location Management System

Ruison Lean Construction Co., Ltd., Jinan 250000, China

Corresponding author: 谢洪栋,

Web Publishing Date: 2024-06-20

Fund Project: 山东省工信厅企业技术创新项目 202350101848

[1]

Dallasega P, Marengo E, Revolti A. Strengths and shortcomings of methodologies for production planning and control of construction projects: A systematic literature review and future perspective[J]. Production Planning & Control, 2020, 32(4): 1–26.

[2]

朱祥松. 基于CPM的资源约束项目进度安排与挣值分析[D]. 杭州: 浙江大学, 2005.

[3]

任斌, 王晓颖, 冯亦军. BIM技术在北京大兴国际机场东航维修机库中的应用[J]. 建筑科学, 2019, 35(11): 133-137. 

[4]

Benjaoran V, Tabyang W, Sooksil N. Precedence relationship options for the resource levelling problem using a genetic algorithm[J]. Construction management and economics, 2015, 33 (9): 711–723.doi: 10.1080/01446193.2015.1100317

[5]

Hegazy T, Menesi W. Critical path segments scheduling technique[J]. Journal of construction engineering and management, 2010, 136 (10): 1078–1085.doi: 10.1061/(ASCE)CO.1943-7862.0000212

[6]

谭泽涛. 基于关键路径法的项目进度管理研究[J]. 建筑经济, 2019, 40(09): 67-71. 

[7]

Huber B, Reiser P. The marriage of CPM and lean construction[C]//11th International Group for Lean Construction Conference, Virginia Tech, Virginia, USA, 2003.

[8]

Lucko G, Alves TCL, Angelim VL. Challenges and opportunities for productivity improvement studies in linear, repetitive, and location-based scheduling[J]. Construction management and economics, 2014, 32 (6): 575–594.doi: 10.1080/01446193.2013.845305

[9]

Seppänen O, Evinger J, Mouflard C. Effects of the location-based management system on production rates and productivity[J]. Construction management and economics, 2014, 32 (6): 608–624.doi: 10.1080/01446193.2013.853881

[10]

贾真. 信息化环境下基于位置的建设工程施工管理方法应用研究[D]. 重庆: 重庆大学, 2016.

[11]

谢洪涛. 整合LOB与CPM的重复性项目调度方法研究[J]. 项目管理技术, 2013, 11(08): 40-45. 

[12]

Anna Krawczy ń ska Piechna. A concept of an integrated construction planning system involving location-based scheduling technique[J]. The Technical Transactions civil engineering, 2014, 2-B: 209-216.

[13]

Stradal O, Cacha J. Time space scheduling method[J]. Journal of the Construction Division, 1982, 108(3): 445-457.doi: 10.1061/JCCEAZ.0001056

Metrics
  • PDF Downloads(0)
  • Abstract views(41)
  • HTML views(20)
Catalog

Figures And Tables

Research on Application of Construction Schedule Based on Location Management System

Juting Tang, Hongdong Xie, Guangxing Wang, Guoping Peng

  • Copyright © Journal of Information Technologyin Civil Engineering and Architecture Editorial Office
  • 京ICP备17057008号
  • Address:No.30 Bei San Huan Dong Lu,Beijing 100013,China
  • Tel:010-64517910 Postcode:100013
  • Wechat:tmjzgcxxjs  QQ:3676678954  E-mail:tmqk@cgn.net.cn