2019, 11(3): 33-37. doi: 10.16670/j.cnki.cn11-5823/tu.2019.03.06
基于BIM技术的某混凝土框架结构机房改造设计
上海溧鹏建设工程集团有限公司,上海 200333 |
Reconstruction Design of a Concrete Frame Structured Machine House Based on BIM Technology
Shanghai Lipeng Construction Engineering Group Co., Ltd., Shanghai 200333, China |
引用本文: 黄晓东. 基于BIM技术的某混凝土框架结构机房改造设计[J]. 土木建筑工程信息技术, 2019, 11(3): 33-37. doi: 10.16670/j.cnki.cn11-5823/tu.2019.03.06
Citation: Huang Xiaodong. Reconstruction Design of a Concrete Frame Structured Machine House Based on BIM Technology[J]. Journal of Information Technologyin Civil Engineering and Architecture, 2019, 11(3): 33-37. doi: 10.16670/j.cnki.cn11-5823/tu.2019.03.06
摘要:本文论述了基于BIM技术的某混凝土框架结构机房改造加固流程,根据既有建筑现状,运用Revit软件建立模型,实现三维可视化协同工作,从管线优化、碰撞检测(如柱与管线、窗的碰撞,梁与管线的碰撞等)等方面实现建筑改造方案优化,运用Revit中的日照分析功能,有助于合理地布置房间、隔墙材质等,将BIM技术运用于既有建筑的加固改造,可以避免传统加固改造中遇到的变更。
Abstract: This paper illustrates the reinforcement and transformation process of a concrete frame structured machine house based on BIM technology. A BIM model is established by using Revit based on the current situation of existing buildings to realize the 3D visualization and collaborative work. The optimization of building renovation plans was achieved from the aspects of pipeline optimization, collision detection (such as collision of column with pipeline and window, collision of beam with pipeline, etc.) and so on. The sunshine analysis function in Revit is helpful to rationally arrange the room, partition material, and etc. The application of BIM technology in the reinforcement of the existing building will avoid changes encountered in the traditional reinforcement and reconstruction.
[1] |
李鑫. Revit完全学教程2016[M].北京:中国建筑工业出版社. |
[2] |
王永图.基于BIM技术的成都市既有大中型商业建筑综合性改造研究[D].西南交通大学, 2016 |
[3] | |
[4] | |
[5] |
Wang C, Cho Y K, Gai M. As-is 3D thermal modeling for existing building envelopesusing a hybrid LIDAR system[J].Journal of Computing in Civil Engineering, 2012, 27(6): 645-656. |
[6] |
Tu K J, Chu S K. Applications of the Open Building Renovation System and BIM Technology in the Sustainable Renovation of Existing Apartment Buildings in Taiwan[C].ETH Conference; The future of open building; September 9-11, 2015. |
[7] |
Danny V, Tu K J. Utilizing Building Information Modeling on the Energy Management of Existing Building[J].物業管理學會論文集, 2015:291-303. |
[8] |
Godager B A. Analysis of the information needs for existing buildings for integration inmodern BIM-based building information management[J].2011, 20: 88-96. |
[9] |
Iiter D, Ergen E. BIM for building refurbishment and maintenance:current status andresearch directions[J].Structural Survey, 2015, 33(3): 228-256.doi: 10.1108/SS-02-2015-0008 |
[10] | |
[11] |
丁宁, 王倩, 陈明九.基于三维激光扫描技术的古建保护分析与展望[J].山东建筑大学学报, 2010, 03: 274-276. |
[12] | |
[13] |
赵华英, 叶红华, 赵冠一, 等.上海玉佛禅寺修缮与改扩建工程中的BIM技术拓展应用[J].土木建筑工程信息技术, 2014, 6(1): 101-105. |
计量
- PDF下载量(27)
- 文章访问量(1981)
- HTML全文浏览量(853)