2018, 10(4): 41-47. doi: 10.16670/j.cnki.cn11-5823/tu.2018.04.07
BIM技术在运河宿迁港项目中的应用
中电建建设集团有限公司,北京 100120 |
Application of BIM Technology in the Suqian Canal Port Project
Power China Construction Group Ltd., Beijing 100120, China |
引用本文: 李欣宇, 何宇航, 霍旭薪. BIM技术在运河宿迁港项目中的应用[J]. 土木建筑工程信息技术, 2018, 10(4): 41-47. doi: 10.16670/j.cnki.cn11-5823/tu.2018.04.07
Citation: Li Xinyu, He Yuhang, Huo Xuxin. Application of BIM Technology in the Suqian Canal Port Project[J]. Journal of Information Technologyin Civil Engineering and Architecture, 2018, 10(4): 41-47. doi: 10.16670/j.cnki.cn11-5823/tu.2018.04.07
摘要:以江苏宿迁港及仓储一期工程项目为依托,结合设计要求高、方案复杂、时间紧张、绿色施工的特点,针对传统施工所遇到的问题,利用BIM(建筑信息模型)技术,在现场大量使用高新信息化施工技术,实现复杂工程可视化,进行参数化建模,利用虚拟三维模型模拟施工,发现问题及时调整;得到最准确的工程基础数据,能够对全过程实现造价管理;工程数据在全过程被共享和重复利用;全力保证工程满足绿色建筑评价要求。结合宿迁港项目,进一步研究了BIM技术在施工阶段的具体应用,包括深化设计应用、可视化技术、与高科技技术结合、5D技术等。
Abstract: This paper mainly focus on the Suqian Port and Warehouse Project Phase Ⅰ. Considering the high design requirements, complex scheme, limited construction period and green construction requirement, the BIM technology is applied to solve the problems met in the construction period. Numerous high-tech informatized construction technologies are applied to achieve the visualization and parameterized modeling for the complicated engineering. A virtual 3D model is applied to simulate the construction progress, aiming at discovering potential problems and solving them in advance. Accurate engineering data are obtained to implement the cost management in the whole process. Engineering data are shared and reused throughout the whole process, and efforts are made to meet the requirements of green building evaluation. Further investigation on the BIM application in the Suqian Port Project includes its applications in areas of deepening design, visualization, integration with other high-tech, 5D BIM, and etc.
[1] |
陈丽娟, 骆汉宾, 辛宏妍.基于BIM的大型博览项目全寿命周期管理平台开发与应用[J].土木工程与管理学报, 2015, (03):54-61.doi: 10.3969/j.issn.2095-0985.2015.03.011 |
[2] |
刘占省, 李斌, 王杨, 卫启星.BIM技术在多哈大桥施工管理中的应用[J].施工技术, 2015, (12):76-80.doi: 10.7672/sgjs2015120076 |
[3] |
刘占省, 王泽强, 张桐睿, 徐瑞龙.BIM技术全寿命周期一体化应用研究[J].施工技术, 2013, (18):91-95. |
[4] |
陈佳佳, 朱燕.BIM技术在天津永基花园二期项目中的应用[J].土木建筑工程信息技术, 2015, 7(6):96-100. |
计量
- PDF下载量(29)
- 文章访问量(2046)
- HTML全文浏览量(790)