Citation: Juting Tang, Hongdong Xie, Guangxing Wang, Guoping Peng. Research on Application of Construction Schedule Based on Location Management System. Journal of Information Technologyin Civil Engineering and Architecture, 2024, 16(3): 41-45. doi: 10.16670/j.cnki.cn11-5823/tu.2024.03.08
2024, 16(3): 41-45. doi: 10.16670/j.cnki.cn11-5823/tu.2024.03.08
Research on Application of Construction Schedule Based on Location Management System
Ruison Lean Construction Co., Ltd., Jinan 250000, China |
The traditional planning method, the Critical Path Method(CPM)is deficient in the management of continuous production flow and resource allocation. Location-based management system (LBMS) can compensate for such deficiencies. Based on actual project cases, this paper analyzed and improved CPM schedule by applying LBMS with the authors' independent development. The result of the study showed that LBMS could establish continuous workflows, balance production rate, optimize resources allocation without much interruptions or affecting project duration. Furthermore, LBMS schedules were optimized with fewer planning elements, hence its flowline graph had a concise and intuitive effect, facilitated communication among all parties.
[1] |
Dallasega P, Marengo E, Revolti A. Strengths and shortcomings of methodologies for production planning and control of construction projects: A systematic literature review and future perspective[J]. Production Planning & Control, 2020, 32(4): 1–26. |
[2] |
朱祥松. 基于CPM的资源约束项目进度安排与挣值分析[D]. 杭州: 浙江大学, 2005. |
[3] |
任斌, 王晓颖, 冯亦军. BIM技术在北京大兴国际机场东航维修机库中的应用[J]. 建筑科学, 2019, 35(11): 133-137. |
[4] |
Benjaoran V, Tabyang W, Sooksil N. Precedence relationship options for the resource levelling problem using a genetic algorithm[J]. Construction management and economics, 2015, 33 (9): 711–723.doi: 10.1080/01446193.2015.1100317 |
[5] |
Hegazy T, Menesi W. Critical path segments scheduling technique[J]. Journal of construction engineering and management, 2010, 136 (10): 1078–1085.doi: 10.1061/(ASCE)CO.1943-7862.0000212 |
[6] | |
[7] |
Huber B, Reiser P. The marriage of CPM and lean construction[C]//11th International Group for Lean Construction Conference, Virginia Tech, Virginia, USA, 2003. |
[8] |
Lucko G, Alves TCL, Angelim VL. Challenges and opportunities for productivity improvement studies in linear, repetitive, and location-based scheduling[J]. Construction management and economics, 2014, 32 (6): 575–594.doi: 10.1080/01446193.2013.845305 |
[9] |
Seppänen O, Evinger J, Mouflard C. Effects of the location-based management system on production rates and productivity[J]. Construction management and economics, 2014, 32 (6): 608–624.doi: 10.1080/01446193.2013.853881 |
[10] |
贾真. 信息化环境下基于位置的建设工程施工管理方法应用研究[D]. 重庆: 重庆大学, 2016. |
[11] | |
[12] |
Anna Krawczy ń ska Piechna. A concept of an integrated construction planning system involving location-based scheduling technique[J]. The Technical Transactions civil engineering, 2014, 2-B: 209-216. |
[13] |
Stradal O, Cacha J. Time space scheduling method[J]. Journal of the Construction Division, 1982, 108(3): 445-457.doi: 10.1061/JCCEAZ.0001056 |
Metrics
- PDF Downloads(10)
- Abstract views(627)
- HTML views(365)