变电站工程施工管理中的BIM应用与实践-以泰州文东高山220KV变电站为例

Application of BIM Technology in Transformer Substation Engineering Construction Management-Taking Taizhou 220 kV Substation Construction Project as Example

  • 摘要: 变电站是电网工程的重要组成部分,对社会民生和生产有巨大的影响。虽然变电站的建筑结构本身相对比较简单规整,但是相关设备种类繁多,线路布置相对复杂,施工难度也较大。在项目施工过程中难免会出现考虑不全面、现场返工浪费和进度滞后的情况。建筑信息模型技术在工程施工管理中的应用,是解决上述问题的途径之一,文章以泰州文东高山220KV变电站工程为例,展开相关实践工作。

     

    Abstract: The transformer substationis an important componentin the power grid project, which greatly impacts the social people's livelihood and production.The structure of the substation itself is relatively simple and regular, but with various kinds ofrelated equipment and complex circuit layout, theconstruction of substation also faces some difficulties. Inevitably, there will be some incomplete design considerations, on-site rework wastes, and progress laggings. The application of building information model technology in engineering construction management is one of the approaches to solve the above problems. This paper takes the Wendonghigh mountain 220KV substation project in Taizhou as an example, to illustrate the relative works with BIM application.

     

/

返回文章
返回