Citation: Niu Feng, Su Yuan, Zhou Xiangyu, Yang Jun. Risk Control Analysis of Metro Entrance /Exit Tunnel Constructed by Pipe Jacking Method in Wuhan. Journal of Information Technologyin Civil Engineering and Architecture, 2015, 7(2): 89-96.
2015, 7(2): 89-96.
Risk Control Analysis of Metro Entrance /Exit Tunnel Constructed by Pipe Jacking Method in Wuhan
1. | Chinese Railway Company, Beijing 100844, China |
2. | School of Civil Engineering and Mechanics, Huazhong University of Science and Technology, Wuhan 430074, China |
According to practical construction case of No.3 and No. 4 entrance / exit tunnel of Zongguan station in the 1st phase of Wuhan Metro Line 3, this paper gives a comprehensive analysis of all kinds of possible emerging risks in the construction process combining the practical monitoring data. Considering that the pipe jacking construction technology has not been widely used in soft soil area like Wuhan, and the constructors lack experience of pipe jacking construction, it would be necessary to the all construction process if related personnel take some actions to prevent and control the existing risk problems in the construction technology. Meanwhile, it could also offer the valuable experiences to similar projects in the future. Through analyzing the process of pipe jacking and practical monitoring data in No. 4 entrance / exit tunnel of Zongguan station, we could draw the following conclusions : (1) Laying the monitoring points in different places of the construction site could effectively avoid the occurrence of risk; (2) During the construction process of No. 4 entrance / exit tunnel, the ground settlement is much larger than the surrounding buildings settlement, the maximum could reach 58.58 mm, and it would gradually increase with the advance of pipe jacking. (3) The settlement of the bridge pier around the tunnel constructed by Rectangular Pipe Jacking Method is very small. The settlement of the bridge pier is far less than 2mm, and the settlement value keeps stable in general.
[1] |
陈聪, 郑新定, 陈扬勋等.武汉首例矩形顶管地铁出入口施工监测及数值模拟分析[J].隧道建设, 2013, 33(5):354-361. |
[2] |
丁烈云, 周诚.复杂环境下地铁施工安全风险自动识别与预警研究[J].中国工程科学, 2012, 14(12):85-93.doi: 10.3969/j.issn.1009-1742.2012.12.016 |
[3] |
王霆, 刘维宁, 张成满等.地铁车站浅埋暗挖法施工引起地表沉降规律研究[J].岩石力学与工程学报, 2007, 26(9):1855-1861. |
[4] | |
[5] | |
[6] |
刘成伟, 刘招伟, 余永强.某地铁车站群洞法施工地表沉降监测分析[J].西部探矿工程, 2008, 20(3):138-140. |
[7] |
黎永索, 阳军生, 张可能等.弧形密排大直径管群顶管地表沉降分析[J].中南大学学报(自然科学版), 2013, 44(11):4687-4693. |
[8] |
方从启, 李向红.浅层顶管施工引起地面沉降的预测[J].江苏理工大学学报(自然科学版), 1999, 20(6):5-8. |
[9] |
陶龙光, 刘波, 城刚等.盾构过地铁站施工对地表沉降影响的数值模拟[J].中国矿业大学学报, 2003, 32(3):27-31. |
[10] |
王远征. 某基坑施工全过程邻近建筑物沉降控制研究[D]. 武汉: 华中科技大学, 2012. |
Metrics
- PDF Downloads(13)
- Abstract views(1377)
- HTML views(780)