Citation: Su Bin, Su Yi, Zhao Xuefeng, Wang Lei. The Application and Exploration of Building Information Modeling(BIM) in Subway Station Project. Journal of Information Technologyin Civil Engineering and Architecture, 2013, 5(6): 95-100.
2013, 5(6): 95-100.
The Application and Exploration of Building Information Modeling(BIM) in Subway Station Project
1. | Beijing MTR Construction Administration Corporation, Beijing 100037, China |
2. | Beijing University of Technology, Beijing 100124, China |
3. | Jiangxi University of Science and Technology, The Institute of Economics and Management, Ganzhou 341000, China |
As an important part of building industry transformation upgrade, BIM technology was used widely in large complicated project.The subway station project is characterized by huge quantity, complex pipeline systems, and difficult equipment installation.This paper introduces the concrete application in three phases like design phase, construction phase and maintenance phase.BIM technology was introduced into the project all-around, which help build the subway station all professional model to realize the professional 3D visualization and make organic connection of each professional flat vertical profile control drawing information is established.Collisions inspection among different professions, the virtual simulation and 4D virtual construction technologies will improve the working efficiency and save the project cost.BIM technology in the application of subway station project can help promote BIM technology to widely use in complicated engineering project and play a reference.
[1] |
柳娟花, 李艳妮.基于BIM的虚拟施工技术应用探究[J].电脑知识与技术, 2011, 7(29):7266-7268.doi: 10.3969/j.issn.1009-3044.2011.29.087 |
[2] | |
[3] |
Eastman C, Teicholz P, Sacks R.BIM Handbook:A Guide to Building Information Modeling for Owners, Managers, Designers, Engineers and Contractors[M].NY John Wiley and Sons, 2008: 93-460. |
[4] | |
[5] |
Eastman C, Teicholz P, Sacks R.BIM Handbook:A Guide to Building Information Modeling for Owners, Managers, Designers, Engineers and Contractors[M].NY John Wiley and Sons, 2008: 93-460. |
[6] |
王广斌, 张洋, 谭丹.基于BIM的工程项目成本核算理论及实现方法研究[J].科技进步与对策, 2009, 21(26):47-49. |
[7] |
马洪娟, 姚守俨, 戈祥林, 林忠和.BIM技术在南宁规划展示馆项目施工中应用体会[J].土木工程信息技术, 2011, 12(3):82-86. |
[8] |
张建平, 范喆, 王阳利, 黄志刚.基于4D-BIM的施工资源动态管理与成本实时监控[J].施工技术, 2011, 4(40):37-40. |
[9] | |
[10] |
王广斌, 张洋, 姜阵剑, 张俊生.建设项目施工前各阶段BIM应用方受益情况研究[J].山东建筑大学学报, 2009, 10(24):438-442. |
Metrics
- PDF Downloads(18)
- Abstract views(1636)
- HTML views(694)