Citation: Cao Le, Xu Hantao, Qu Jing, Fang Ligang, Huo Guanghui, Chen Jiangwei, Tang Xinyuan. BIM Application in Wuhan Greenland Center Lifting Steel Platform Mold Installation. Journal of Information Technologyin Civil Engineering and Architecture, 2014, 6(5): 38-45.
2014, 6(5): 38-45.
BIM Application in Wuhan Greenland Center Lifting Steel Platform Mold Installation
1. | CABR Technology CO., LTD., Beijing 100013, China |
2. | China Construction Third Engineering Bureau CO., LTD, Wuhan 430023, China |
Wuhan Greenland Center Project is the world's third-tallest building with 636 meters.The underground structure has been completed and the main building structure is under rapid construction.During the construction, BIM is playing a key role.This paper introduces the method of setting the jacking formwork system based on BIM technology, and solves problems of BIM application to vertical transportation, turnover materials management, pipeline optimization and steel structure erection.BIM technology makes the installation of the tower crane lifting formwork platform go on smoothly and guarrantees the construction progress on the ground core tube structure.
Metrics
- PDF Downloads(20)
- Abstract views(1128)
- HTML views(987)