模拟技术在黄骅港煤码头三期工程设计中的应用
中交第一航务工程勘察设计院有限公司, 天津 300222 |
Application of Simulation Technique in Design of Phase 3 Coal Terminal at Huanghua Port
CCCC First Harbor Consultants Co., Ltd., Tianjin 300222, China |
引用本文: 杨兴晏. 模拟技术在黄骅港煤码头三期工程设计中的应用[J]. 土木建筑工程信息技术, 2013, 5(4): 114-118.
Citation: Yang Xingyan. Application of Simulation Technique in Design of Phase 3 Coal Terminal at Huanghua Port[J]. Journal of Information Technologyin Civil Engineering and Architecture, 2013, 5(4): 114-118.
摘要:为满足国家对环境保护的高要求,在黄骅港煤码头三期工程的设计中,一航院提出了采用密封性能较佳的筒仓替代露天式煤堆场的设计方案。由于在煤码头中大规模的采用筒仓群在国内外尚属首次,有许多技术问题需要研究。本文结合该工程的实例,介绍了如何应用计算机模拟模型合理确定筒仓规模,并就在该码头采用旋转式装船机兼顾两侧装船泊位的设计方案是否可行进行了研究。
Abstract: To meet the stringent national requirement for protection of environment, FHC has proposed a design of silo with better enclosing feature instead of exposed coal stockyard forsthe Phase 3 Coal Terminal at Huanghua Port. As it is the first time to use silos on large scale in coal terminals of China, many technical issues need to be solved by researches and studies. The present paper introduced the determination of silo size by using computer simulation model, by giving practical examples in the engineering practice. The paper has also discussed design study of slewing ship loader for loading vessels at both sides of the coal berth.