Citation: Yuan Bohong, Zhang Zhuo, Ma Xijun, Wei Xiaohuan, Gao Zhiwei. Integration of BIM Design, Construction, Operation and Maintenance in Maike Commercial Center Project. Journal of Information Technologyin Civil Engineering and Architecture, 2016, 8(3): 53-56. doi: 10.16670/j.cnki.cn11-5823/tu.2016.03.10
2016, 8(3): 53-56. doi: 10.16670/j.cnki.cn11-5823/tu.2016.03.10
Integration of BIM Design, Construction, Operation and Maintenance in Maike Commercial Center Project
Northwest Manager Division of Installation Business Department, China Construction Third Engineering Bureau Co., Ltd., Xi′an 710000, China |
Xi′an Maike Commercial Center is the first all-steel complex in the northwest area. BIM design, construction, operation and maintenance are integrated throughout the project life cycle. BIM technology is applied as early as in the design phase, and in addition to the basic design of the pipeline, the comprehensive arrangement optimizes the clear height, and also involves all aspects of hanger design, visualization correspondent, construction simulation, construction management and pre-processing factory. As a carrier, the project uses three-dimensional collaborative mode, and implements the BIM technology in the project, which greatly improves the construction quality, facilitates construction management, shortens the construction period, and lays a solid foundation for the operation and maintenance management of later stages.
[1] |
BIM工程技术人员专业技能培训用书编委会. BIM建模应用技术[M].中国建筑工业出版社, 2016. |
[2] |
丁烈云, 丁士邵. BIM应用·施工[M].同济大学出版社, 2015. |
[3] |
何关培. BIM总论[M].中国建筑工业出版社, 2013. |
[4] |
Autodesk Asia Pte Ltd. Autodesk Revit族达人速成[M]. 2014. |
[5] |
刘庆. Autodesk Navisworks应用宝典[M].中国建筑工业出版社, 2015. |
[6] |
葛清. BIM第一维度[M].中国建筑工业出版社, 2013. |
Metrics
- PDF Downloads(21)
- Abstract views(2158)
- HTML views(865)