PKPM施工管理平台4D虚拟建造应用浅析
建研科技股份有限公司, 北京 100013 |
Application of 4D Virtual Construction based on PKPM Construction Management Platform
CABR Technology Co., Ltd., Beijing 100013, China |
引用本文: 刘昭, 曲径. PKPM施工管理平台4D虚拟建造应用浅析[J]. 土木建筑工程信息技术, 2015, 7(6): 37-42. doi: 10.16670/j.cnki.cn11-5823/tu.2015.06.08
Citation: Liu Zhao, Qu Jing. Application of 4D Virtual Construction based on PKPM Construction Management Platform[J]. Journal of Information Technologyin Civil Engineering and Architecture, 2015, 7(6): 37-42. doi: 10.16670/j.cnki.cn11-5823/tu.2015.06.08
摘要:本文针对目前在工程建设项目进度管理中存在的问题进行了深入分析,提出了把基于BIM的虚拟建造技术与工程建设项目进度管理相结合的思维模式,并利用PKPM施工管理平台,逐点解决进度管理中的关键难题。基于PKPM施工管理平台在工程建设中的应用,通过与传统施工项目进度管理存在问题的对比,从精细化管理、直观展示、进度模拟及工程量分析上,阐述了4D虚拟建造技术在施工进度管理方面的优势,以真实的BIM平台为依托,使论述更具有说服力。本文所有论述观点均通过实际工程检验,由此可见,基于BIM的虚拟建造技术会对我国工程项目管理的发展产生积极的影响。
Abstract: In this paper, the problems in the progress management of engineering construction projects are analyzed, and the thinking mode of the combination of BIM-based virtual construction technology and construction project schedule management is put forward. The key problems in the progress management are solved by using PKPM construction management platform. Based on PKPM construction management platform in the construction of the application, through the comparison with the traditional construction project schedule management, and fine management, visual display, progress simulation and engineering analysis, this paper expounds the 4D virtual construction technology in the construction schedule management with the real BIM platform as the basis, which makes the discussion more convincing. This paper is based on the actual engineering test, which shows that the virtual construction technology based on BIM will have a positive impact on the development of engineering project management in China.
[1] |
徐伟, 李建伟.土木工程项目管理[M].上海:同济大学出版社, 2000:447-516. |
[2] | |
[3] |
ChuckEastman, PaulTeicholz, RafaelSacks(Eds.).BIM Handbook:A Guideto Building Information Modeling for Owners, Managers, Designers, Engineers and Contractors[M], New York: John Wileyand Sons, 2008:233-244. |
[4] |
王广斌, 张洋, 杨学英等.工程项目建设信息化发展方向—虚拟设计与施工[J].武汉大学学报(工学版), 2008, 41(2):90-93. |
[5] |
王青薇, 张建平.基于BIM的工程进度计划编制[J].商场现代化, 2010(35):220-222.doi: 10.3969/j.issn.1006-3102.2010.35.157 |
[6] |
乐云.项目管理概论[M].北京:中国建筑工业出版社, 2008: 204-225. |
[7] |
Eastman C, Teicholz P, Sacks R, etc. BIM handbook: aguide to building information modeling for owners, managers, designers, engineers, and contractors [M].2nd ed. New Jersey: John Wiley & Sons, 2011:13. |
计量
- PDF下载量(15)
- 文章访问量(2107)
- HTML全文浏览量(849)